SMT Auto Placement
Category: Surface Mount
Description: SMT Auto Placement is the process of installing Surface Mount (SMT) components on the surface of the PCB by machine. (See also: SMT Hand Placement)
Major Cost Drivers -- PCBA SMT Auto Placement
Process Time = Travel Time + Load Time +
Fiducial Check Time + Device Placement Time + Unload Time
- Travel Time = Shuttle Conveyor Time + Transport Conveyor Time
- Shuttle Conveyor Time = Shuttle Conveyor Length/Shuttle Conveyor Speed
- Shuttle Conveyor Length = (Machine variable)
- Shuttle Conveyor Speed = (Machine variable)
- Transport Conveyor Time = (Transport Conveyor Length/Transport Conveyor Speed)* Transport Conveyor Quantity
- Transport Conveyor Length = (Machine variable)
- Transport Conveyor Speed = (Machine variable)
- Transport Conveyor Quantity = (Machine variable)
- Shuttle Conveyor Time = Shuttle Conveyor Length/Shuttle Conveyor Speed
- Load Time = Machine Load Time*Machine Quantity
- Machine Load Time = (Machine variable)
- Machine Quantity = (Machine variable)
- Fiducial Check Time =(Machine variable)*Machine Quantity
- Device Placement Time = Quantity Component Type/Component Type Disposition Rate
- Unload Time = (Machine variable)*Machine Quantity
User Inputs –- PCBA SMT Auto Placement
PSO: Fixture Requirements override. (Adds fixture load / unload time to Machine Load / Unload time if true.)